EXPATRIATE TIMELINE

S/N Activity Timeline Number Of Days Total Number Of Days For Processing
 1  Receipt and forwarding of Applications   First Week  7 Days  7 Days
 2  Appraisal of Application by Briefing officers  Second Week  7 Days 14 Days 
 3  Verification and Processing of application for Approval  Third Week  7 Days 21 Days
 4  Approval within DCB's approval limit / Processing to Permanent Secretary  Fourth Week  7 Days 28 Days
 5  Approval within Permanent Secretary's approval limit / Processing to Honorable Minister  Fifth - Sixth Week  14 Days  42 Days
 6  Approval by the Honorable Minister of Interior  Seventh - Eight Week 14 Days  56 Days 
7 Days